ARCHERFIELD AIRPORT UPGRADE – EARLY WORKS

  • CATEGORY: AIRPORT WORKS, LANDSCAPING, ROADS AND CIVIL INFRASTRUCTURE
  • PROJECT VALUE: $300k
  • LOCATION: Archerfield Airport, Brisbane
  • COMMENCED: 01 Nov, 2020
  • COMPLETED: 20 Dec, 2020

Following on from the success of the previous 2 stages, OM Civil were awarded the Archerfield Airport Project AIM: Airside Infrastructure Modernisation (Project AIM) early works contract.  Works involved Airside stormwater upgrades and bulk earthworks.  The project was carried out in accordance with all ABC guidelines and approvals.